Kitchen Prep Dependency Schedule Calculator

Quick Answer

Work backward from a kitchen deadline. In the example, 10 minutes of setup, two parallel prep tracks of 35 and 50 minutes, and 20 minutes of final work need an 80-minute window.

Use Calculator · Read Guide

Enter Your Details

Enter one shared setup, two prep tracks that can run together, and one final stage that must wait for both.

Calculator Inputs

Your Calculated Result

Advertisement

Kitchen Prep Dependency Schedule Calculator Guide

Map the Work Before Entering Times

Write down the work that has to happen before either prep track starts. That work goes in shared setup, such as setting out equipment or collecting ingredients for both tracks. Use one track for each branch that can proceed on its own after setup. Keep the activity labels on your worksheet so people can tell what each track includes. Enter only the time needed to complete each phase.

Check That Both Tracks Can Run Together

Two tasks can be independent on paper and still need the same person, tool, or open work surface. Treat them as parallel only if you have the resources to run them together. Once that condition is met, the shorter track can finish while the other continues. If one worker must do both tracks in full, put their combined duration in one track and enter zero for the other.

Use the Longer Track at the Join

Final work has to wait for the last track to finish, so take the larger of the two prep times. Add setup and final work once. This gives the elapsed duration for the whole plan. Then subtract it from the deadline to find the latest setup start. Time for the shorter track before final work starts equals the longer duration minus the shorter duration.

Elapsed minutes = shared setup + the longer prep track + final work.

Two Prep Tracks, One FinishTen minutes of setup lead to two parallel tracks of 35 and 50 minutes. Both must finish before the final 20 minutes.Two Prep Tracks, One FinishSetup10 minTrack A35 minTrack B50 minFinal Work20 min
Ten minutes of setup lead to two parallel tracks of 35 and 50 minutes. Both must finish before the final 20 minutes.

Example With a Noon Finish

Suppose setup takes 10 minutes, Track A takes 35, Track B takes 50, and assembly takes 20. The total is 10 plus 50 plus 20, or 80 minutes. Start setup at 10:40 to finish by noon. Both tracks begin at 10:50. Track A ends at 11:25, Track B at 11:40, and assembly starts at 11:40. The 15-minute difference gives Track A some room before it determines the start of assembly.

Read Earlier-Day Times and Equal Tracks

If a deadline is shortly after midnight, the start can fall on the previous day or earlier. The result labels each earlier clock time so you can put it on the correct date. If both tracks take the same time, both are limiting and either delay pushes final work later. When a phase has no work, enter zero for that phase. The model uses whole minutes in one local clock and treats days as 24 hours.

Which Track Controls the Finish?Track A takes 35 minutes and Track B takes 50. Track A has 15 minutes before it would delay final work.Which Track Controls the Finish?Track A35Track B50
Track A takes 35 minutes and Track B takes 50. Track A has 15 minutes before it would delay final work.

Separate Elapsed Time From Staffing

Two parallel tracks need different resources during some of the same minutes. The 80-minute result is elapsed time, not 80 staff-minutes. Calculate staff effort separately, especially when an activity uses two people or includes unattended time. This worksheet supports one fork and one join. Use a fuller schedule for several joins, equipment queues, staggered staff arrival, or tasks that must start before shared setup is complete. Start earlier when you need uncertainty to fit inside the deadline.

Advertisement

Frequently Asked Questions

Which Time Do I Enter for Each Track?

Enter the total elapsed time from its start to its completed output, including any required waits.

Can One Track Have Zero Minutes?

Yes. Use zero when all prep follows one track.

Does Every Task Need Two People?

Use people and equipment you have available. The worksheet does not assign them.

What Does the Controlling Track Mean?

It determines when final work can begin. If both tracks finish together, either delay changes the finish.

Can This Plan More Than Two Tracks?

Group serial steps inside each track, or use a wider scheduling model for more branches.